Welcome      
Welcome
Photo Tour
What's It Like?
Get in Touch!
     

 05 November, 2002

Well, well, well - the Well is well

Finally!!! We finished our well! After 2 months of digging and frustrations, we have water at the top! We had started the first dig near the plateau and dug ~40 feet deep until we decided to stop and look elsewhere. So we dug at the bottom of the property, and ~20 feet later found water. As luck would have it, we also found oil - no I mean coral where the water was...thus giving us a truly filtered water!!

So now the question on everyone's mind is: How do they find water / dig wells in your country? Answer: the old fashioned way!!

Finding the location of the well is up to one of a few local indians that have the 'gift' of finding water. They place a piece of metal wire in front of the waist and walk around until it bends and contorts. When it does that, you start digging.

With the bulldozer? With a drill? NO. That would be TOO easy! They dig wells by hand. It takes about three guys, one shovel, one bucket, one rope and several weeks. One guys digs, while the others pull the dirt / sand / rock with the bucket attached to the rope. This process is relatively easy during the first few meters, but gets extremely difficult as the hole gets deeper. The hole is about 4 feet in diameter - and straight down. Once water has been reached, they lower the cement tubes one by one and then dig a few more feet inside the tubes until there are about 6 feet of water. The trick then is to dig faster than the water comes in! In our case, because of the coral (which is like stone), it took several weeks to do those last few feet of digging.

Once the tubes were in and the water in the well, we installed a 1 HP submersible pump and 500 feet of wiring and plumbing to pump it up to the top. Right now, since we still do not have electricity, so we are using a gas powered electric generator (thanks Jonathan!) to pump up the water.

It may sound silly...but we are so excited to have water...take NOTHING for granted!!!!

We have a road...or does it have us?...
It was supposed to take 3 weeks...it actually lasted 4 months, but we now have a road. After several weeks of cutting it out with the bulldozer, 92 truck loads of riverbed rock, and all sorts of challenges along the way - our road is now functional. It rises over 150ft from the main road and is about 600 meters in length. Trucks and 4 wheel drive vehicles have been coming up and down now for several weeks. Regular 2 wheel cars can go up, but only during the dry season.

Although the road is officially 'complete', it is in fact only the beginning of a long struggle of continuous maintenance and continuing challenges. It is steeper than most engineers would recommend and the risks of erosion and wash are significant. Our main problem right now is water runoff. We had a significant rainstorm a few weeks ago and lost several cubic meters of road in several areas! This was not a complete surprise as we expect to have issues until we learn where the problems are are eventually train the water to go where we want it to go. We are doing this placing drainage and culverts in certain strategic areas to remove the water far away from the road. In certain areas, the drainage ditches are being cemented with large rocks to slow the speed of the running water. The scary thought is that in one significant rainstorm, an entire portion of the road can be washed away.

Until we are confident that the water drainage and erosion issues have been well addressed and controlled, each time it rains hard (day or night - even at 3 am!!), we go to the finca to observe the water flow and fine tune small issues before they become significant problems.

All in all, this was and will have been the biggest, most challenging and most important project that we have undertaken towards our goal of building our own paradise!

Home Construction Begins
Since the road has been completed and we can haul materials up to the top, we have begun construction of the house. As of this writing, we are just completing the foundation. It is about 1 meter underground and 1 meter wide at each post. Each post will tied together underground by steel rods in all directions. This is a common design in earthquake prone areas.

Once the foundation will be complete, it should be relatively quick assembling the structure. All the wood and posts are on the site and have been cut to fit.

We expect to complete the house by April 2003...we'll see and let you know!

OUI OUI Update
Oui Oui is missing. After all, he did survive his first weeks with Maya, but now that he is growing older and bigger, he decided to have a social life and check out the other dogs in the neighborhood. We are on the lookout for him and are asking everyone if they have seen him. If he is found, we will, of course, let you know.









Previous Post
30 October

Next Post
22 November



Schedule

November
Begin structural home construction
Bring power to site.

Continue garden design and planting.

Fix and maintain drainage for water.

Make septic tank.

Manuel in Miami 11-20


2003
Complete home construction


Stay Updated!
Add your name to our mailing list and
receive notifications of site updates.

Click Here


 PHOTOs

Digging a well the old fashioned way

Starting the well...by hand At 6 meters...we found water
Putting in the cement tubes into the well View of a cement tube having just been lowered Making sure it looks good from the top  Going down to make slight adjustmentView from the top of the guys digging the well

Manuel and Nicolas discussing the well pump Manuel checking out the well....don't fall!!!




Construction has begun!!


Placing culverts in the road for water evacuation
  
Emmanuelle and Nicolas Leveling the house with the old fashion water leveler
 The frame on the foundation   Manuel bringing up some plantsFoundation work...with Maya observing





Are you getting site
updates in your email?

A
dd your name to our mailing list and
receive notifications via email.

Click Here